Observations From the Distressed Asset Trail

Posted by Roger Harper in Untagged 

Roger Harper
User Rating: / 0
PoorBest 
Observations From the Distressed Asset Trail

In a previous newsletter, I commented on the challenges of finding distressed assets. I have recently experienced several more REO/distressed asset encounters, as well as collected anecdotes from many of my fellow travelers, and some common themes and traits are emerging that I would like to share.

Banks are now finding themselves in the unfamiliar position of foreclosing on commercial properties. Most institutions have not had a Special Asset or Real Estate Owned (REO) department since the 1990s. The few projects that got into trouble were usually quickly disposed of to an ever-growing economy that was usually willing to pay something close to the outstanding loan balance. Now, prospective buyers are severely limited by the uncertainty of the recession and the lack of available debt.

Unfortunately, in their haste to remove these assets from their books and a lack of experience with asset disposal, banks are failing to effectively maximize the sale price of their REO properties. The negative impact to a bank's capitalization when they take title to a property is forcing them to rush properties to market without proper preparation or with sufficient time in the market for adequate exposure to qualified buyers. The following are observations and comments from my experiences or of others:

Sep 22
2009

Things to Do Differently During the Next Construction Boom

Posted by Roger Harper in Untagged 

Roger Harper
User Rating: / 0
PoorBest 
Things to Do Differently During the Next Construction Boom


Perhaps the "green shoots" of the recovery are sprouting; perhaps it's just the "eye of the storm." Nevertheless, it has prompted thoughts about what we might change when (not if) the next construction boom comes. The construction industry in the United States is approximately $1.23 trillion in annual volume, and it is estimated that there is waste of $123 billion. Let's consider what we might do differently to make the development, design and construction process more successful - delivering projects within budget, on time, and without a hangover of claims and disputes.

Where Does the Fast Track Really Lead?

I have been a participant and advocate in many projects that were constructed and designed using a "fast track" process. Design and permitting were completed in progressive stages in order to facilitate an early construction start; in retrospect, those decisions were always undertaken for the seemingly "compelling need" to get the project to market, or to reduce the interest cost during the construction period. I have always wondered if, after the project is complete, a final, honest accounting of the additional costs of fast tracking would validate the "compelling need." When you consider the change orders due to incomplete pricing documents or lack of design coordination, delays due to inadequate lead time for materials and fabrication, and the ever-present " it wasn't on the bid set" cost changes, you have to wonder if there is ever any reason, short of natural catastrophe or national defense, to undertake a project on fast track.

Let's Level the Playing Field of Information
Once a contractor is awarded a bid, the advantage shifts almost completely in his or her favor. Perhaps a more cynical way to put it is that contractors don't compete for the delivery of the best buildings at the best price, but rather compete for the opportunity to increase their price and protect their profit regardless of the completion of the project. The contractor's bid may be intentionally low in anticipation of weakness in the construction documents that will allow profit to be gained on change orders. Certainly, the fast track process is wide open to this type of abuse. Once the contract is awarded, the owner has no practical leverage to counter the contractor's claim for additional cost or time other than dispute the proposed changes. Terminating the contractor and re-bidding the project is rarely a feasible alternative. The contractor's superior access and control of pricing information places the owner at a severe disadvantage. The solution is a complete "open book" by the contractor, and the owner must have qualified representation and expertise on his or her side to absorb, interpret and question the contractor's proposed changes in a professional, competent manner.

How Do We Get Truly Fixed-Price Contracts?

The risks of a construction project are borne by all the parties and they are unavoidable. The most effective agreement are those aligning the interests and incentives of the parties. One possible alignment of incentives is; if in return for removing the profit incentive from change orders, the contractor's profit of his contracted bid is reasonably protected. How far would that go in reducing disputes and claims? In other words, as long as I (the owner) am not changing the overall scope and beneficial use of my project, and the changes are unanticipated and necessary for the original intent, then I pay only the direct cost of those changes. If you (the contractor) need more time to complete the project or incur additional overhead to implement those changes, I will pay those documentable costs. The contractor's profit is still at risk for buyout and timely completion as originally bid, but the incentive to generate change orders burdened by profit, overhead and fees is removed. In today's construction market, these provisions are attainable.

Conclusion
I believe we have an opportunity to "reset" the construction industry by shifting the paradigm away from adversarial relationships toward a more equitable allocation and sharing of risks between Owner, Contractor and Designer. Let's create methods to place at least as much focus on reducing costs and controlling schedules, as we do now on crafting damage clauses. As we move into the recovery and projects begin to flow once again, let's consider some "out of the box" ideas to make our industry more efficient and create more value in the resulting built environment.


RHarper Consulting Group provides development consulting, program management, and owner representation services.  rharper@rharperconsulting.com

 

Aug 31
2009

If it Seems Too Good to be True…... Contractors are Cutting Prices to Get Jobs— Maybe Too Much!

Posted by Roger Harper in Untagged 

Roger Harper
User Rating: / 0
PoorBest 

   Contractors are Cutting Prices to Get Jobs—

Maybe Too Much!

 

Insider Blogs

Roger Harper Observations From the Distressed Asset Trail written by Roger Harper
Observations From the Distressed Asset TrailIn a previous newsletter, I commented on the challenges of finding distressed assets. I have recently experienced several more REO/distressed asset encounters, as well as collected anecdotes from many of m ...   (Read More)

Roger Harper Things to Do Differently During the Next Construction Boom written by Roger Harper
Things to Do Differently During the Next Construction Boom Perhaps the "green shoots" of the recovery are sprouting; perhaps it's just the "eye of the storm." Nevertheless, it has prompted thoughts about what we might change whe ...   (Read More)

Roger Harper If it Seems Too Good to be True…... Contractors are Cutti ... written by Roger Harper
   Contractors are Cutting Prices to Get Jobs— Maybe Too Much!   I have recently fielded several enquiries about projects that have been in limbo for several months and are now approaching a construction start.  The p ...   (Read More)