Prep (take everything down, put the lights in the dishwasher) - Paint - Maintenance - Cleaning -Carpet.
5 business days for most turns, but we contracted out paint so sometimes had to wait on the contractor to schedule us in, so it usually ended up being about 7 business days. However, you can't do them all at once if you have one team, so they sit until the ones in front of them are completed and move outs seem to bulk up at the end of the month. So if you are talking move out to move in, then that's more like 20-27 days for those that move out the first of the month, but faster end of month.